Permits have been approved! A second, final, round of asbestos abatement was finished. New discoveries continue as floors and walls are opened. With regard to securing the building to the foundation (presently the building simply sits on the foundation) in some places less work will need to be done, in other places the work plan needs to be reconfigured. The internet cable has been replaced by Xfinity after two days with no internet in the building– all is up and running now.