Due to many walls needing to be opened for asbestos abatement, we can now add more electrical outlets and cut down on the use of extension cords. Small wall-heaters are being removed, and will be replaced by mini-split air handlers making our HVAC system more efficient overall. The large dumpster in the parking lot will be replaced by a smaller dumpster next week, taking up fewer parking spaces. Extraneous and outdated land-line phone cables are being removed, and a new more efficient water heater has been installed. Our project liasons, Brian Egan and Nick Houtman are very pleased with the care being taking by the Gerding crew, to communicate with us and to contain costs!