A giant THANK YOU! to all who have already volunteered painting time or signed up to do so on June 13, 14, or 20.
We have completed Phase One of interior painting, and 2/3 of the exterior siding staining. Everything looks clean and fresh!
Commercial painters will paint the new Fire Suppressant Sprinkler System pipes starting (tentatively) July 7. After that 3 – 4 day job, they will also paint the remaining 1/3 of the exterior siding in areas unsafe for volunteers.
We are re-scheduling the planned Move-Back-In weekend from June 28 – 29 to July 19 – 20. Requests and sign-up sheets will start in early July.
Painting Help
Phase Two Painting starts Friday June 13 and Saturday June 14 9 AM – 12 PM and 1 – 4 PM, and Saturday June 20 9 AM – 12 PM and 1 – 4 PM.
We especially need 2-3 people on the 14th 9 – 12 shift, and more help on June 20 both shifts.
(Please sign up on sheets on foyer table or contact Wolfgang)
General Help needed (time TBD)
Tasks include installing many shelves in the mezzanine storage room; installing blinds in windows in all the rooms; installing bulletin boards, fire extinguishers, signs, cabinets.
Contact Wolfgang Dengler in Breeze with questions.